Display the Update EAC Dialog Box

Display the Update EAC dialog box to manually update the forecast values for a control account or work package.

To display the Update EAC dialog box:

  1. Display the Project view.
  2. Click a control account or a work package, and do one of the following:
    • In the Tasks group on the Edit tab, click Update EAC.
    • Right click the Spreadsheet pane, and select Update EAC on the shortcut menu.